If you want to build, you need a binding and regulating contractual situation. When building with reusable components, this remains unchanged. However, new questions may arise during reuse, which are explained and taken into account in the following documents.
These documents were produced as part of the project "Reuse of components: Legal framework" co-financed by Innosuisse (project no. 55734.1 IP- SBM) in collaboration with Zirkular GmbH / baubüro in situ and the Zurich University of Applied Sciences ZHAW, School of Applied Sciences ZHAW, School of Management and Law, Department of Urban Planning and Environmental Law.
The documents are currently only available in German.
03.01 Specialist planning contract for circular construction (ziB)
The specialist planning contract regulates the project definition, the scope of services, the individual contract components as well as the remuneration, deadlines, dates, insurance and liability between the client and the contractor in a binding manner.
03.02 General Terms and Conditions of Contract (AVB) for the Specialist planning contract for circular construction (ziB)
The AVB for the specialist planning contract for circular construction (ziB) specify general points, tasks and services in relation to the source and target objects.
04 Declaration of intent
The letter of intent regulates the rights, obligations and remuneration for the planned takeover of components between the transferor and the interested party.
05 Handover agreement
The handover agreement regulates the organization, remuneration, warranty and liability for the handover of components between the transferor and transferee.
06 Contractual clauses Dismantling
These contractual clauses regulate the dismantling of reusable components as part of a dismantling project by a dismantling company or a
dismantling company.
07 Contractual clauses Reinstallation
These contractual clauses are geared towards the reinstallation of components in the target property. The items are designed in such a way that they can be integrated into corresponding contracts for work and services with construction companies.
08 Factsheet Liability
This factsheet deals with selected liability issues relating to the reuse of components in the context of the dismantling of components and their reinstallation (assembly) in the target object as well as certain special issues.
09 Factsheet Authorization
The factsheet refers to permits that may have to be obtained for the source and target objects and for the storage, collection, transportation and transfer of components to be reused, and classifies these in legal terms.
10 Factsheet on construction product law
The factsheet shows who is subject to which obligations under construction product law and classifies reusable components within its scope.